Collinsville,
Oklahoma
July 6, 2011 S-Curve Re-Alignment Plans |
This web site is brought to you by the Newspaper Museum In Collinsville and the other advertisers appearing on these pages. If you would like to provide news content or advertisements ... call Ted Wright (918) 371-1901 or send email to wrightted@aol.com. 1110 W. Main, Collinsville, OK 74021 Frequently Asked Questions |
Home
(email questions/comments to wrightted@aol.com). Ted Wright -- last update 7/06/2011 (S-CurveDetours.html) www.cvilleok.com Copyright 2011 -- Collinsville, Oklahoma |
Custom
Search
|
Note:
I added the color coding to the construction drawing provided by the city.
I hope I have intrepreted them correctly. -- Ted Wright 7/6/2011 |
HWY
20 Construction Update -- STATUS UPDATES HIGHWAY 20 ALIGNMENT -- 7/01/11
As many citizens realize, there are road crews working on highway 20. They are working on the project known as the highway 20 alignment. Those that live in Collinsville will recognize it as Straightening of the S-curve. This curving stretch of road has been a safety hazard for a long time. The city was involved in relocating the city electric poles and lines, however the project is the Oklahoma Department of Transportations not the City of Collinsville. ODOTs project officially began with the notice to proceed on May 31st and is slated for 180 day completion. In an effort to keep citizens informed, we will update information concerning the ongoing project on a regular basis. Please check back.
Two week projection on Highway 20: Oklahoma Department of Transportations contracted road crews continue to finish up the detour lanes between 14th street and 17th street as well as the north side of highway 20 between 20th street and 22nd Street. The crews are completing the asphalt overlay on these detour lanes. When the asphalt facet is completed the lanes will be striped and traffic will be channeled onto the lanes. East bound traffic will be channeled to 19th & Broadway and may either continue east on Broadway or turn south on 19th and back onto Main Street. West bound traffic on Main Street will also be channeled through 19th Street to the Broadway intersection where traffic then may continue west .
Earthwork will continue to take place between 18th Street and 20th Street as the future alignment route begins to take shape.
The City will continue to update any new information concerning detours as that information becomes available.
Phil Stowell |